In October 2011, AuRico Gold contracted Ledcor to develop and operate the Young-Davidson open-pit gold mine in northern Ontario. Pre-production development started with the first blast in November 2011, and the services Ledcor is providing include:
Since Ledcor has begun operations in October of 2011, over 615,000 hours have passed with a Total Recordable Incident Frequency (TRIF) of 0.97, including several successful gold flag audits.
The mine will have a 15-year life and will produce 180,000 ounces of gold annually. The open pit operations will deliver ore feed to the 6,000-ton-per-day processing mill.